The Regular Meeting of the Housing Authority of the City of Middletown was held in the conference room at 40 Broad St., and via Zoom on Monday, July 11, 2022.
Chairman Noglow called the meeting to order at 5:01 p.m. and called the roll.
PRESENT: Evan Noglow, Chairman; Phil Cacciola, Commissioner; Senovia Stone, Commissioner
ALSO PRESENT: William Vasiliou, Secretary; John Rumberger, Asst. Executive Director; Christine Juraska, Finance Director, Jason Lewellyn, Esq.; Linda Guarino, Section 8 Manager
ABSENT: Larry Riley, Commissioner
PUBLIC SESSION: None
FOLLOW-UP REPORT: None
APPROVAL OF MINUTES: On motion by Commissioner Cacciola, seconded by Commissioner Stone, it was unanimously voted to approve the minutes of the June16, 2022 meeting.
APPROVAL OF BILLS: On motion by Commissioner Cacciola, seconded by Commissioner Stone, it was unanimously voted to approve the bills as submitted.
ACCOUNTS RECEIVABLE: Secretary Vasiliou reported on the June 2022 A/R which shows a decrease of $11,481.85 for CONN 9-2, an increase of $6,760.54 for Conn 9-3, an increase of $16,660.39 for Conn 9-4, a decrease of $584.00 for CONN-5, a decrease of $29,930.93 for State Family, and an increase of $187.10 for E-101.
LEGAL ACTION: Atty. Lewellyn reported on the Legal Report of 6/30/2022. In June 11 Summary Process eviction cases were filed with the court. $0.00 was received in collections.
FINANCIAL: Ms. Juraska reported that she is working on the year end audit.
SECTION 8: Mr. Vasiliou reported that there are 825 units in place, and the average HAP payment is $794.53.
PERSONNEL: None
MAINTENANCE: 171 work orders were completed in June.
MODERNIZATION: Maplewood Window /Door Replacement: physical work is complete; awaiting close-out docs. Traverse Door Replacement: Installation complete; awaiting close-out docs and final acceptance for A/E. Monarca Place HVAC/Generator: Bids under review and awaiting award recommendation from A/E.
Marino Manor Expansion: Bids due July 14; RFI deadline 7/7. Sbona Tower Exterior Façade/Masonry RFQ: RFQ submissions still under review. Sbona Tower HVAC/Switchgear/ Maplewood and Traverse Square domestic water/HVAC piping and controls upgrade RFQ: submissions under review. Office Phone System Upgrade: Awaiting 2 additional quotes for new VOIP phone system. Copper phone line repair obsolete by August 22 per FCC.
SPECIAL REPORTS: None
OLD BUSINESS: None
NEW BUSINESS: None
OTHER BUSINESS: Mr. Vasiliou gave an update on Shepard Home, St. Luke’s and Charles IT